Black Summer, in order

Bridges through the 2019–20 bushfires with the RFS and the Telco Authority. Offshore Tier 1 could declare a major without waiting for Sydney.

Pencil sketch of smoke, a tower, and a restoration order.

RFSRestoration order

The 2019–20 Black Summer fires were not a single incident with a start and a restore. Sites failed in the order the fire chose, often faster than a Sydney morning could be assembled, and the people who needed the network back first were not always the people shouting loudest on the bridge. I ran those bridges with the Rural Fire Service and the Telco Authority.

What we agreed, and then enforced on every handover, was a restoration order. Critical public sites came back before commercial volume. Field, the operator and the offshore teams worked from that list. A new shift was not allowed to invent its own priority because the previous shift had gone home.

The second failure was quieter and just as expensive. Offshore Tier 1 could already see a fault that met the threshold for a major incident, and they waited for Sydney to say the word. That wait is not caution. It is a defect in the operating model. I wrote a triage they could apply on their own shift: the symptom, the number of sites, and a public-safety flag. If it matched, they declared. They did not wait for me to wake up.

I still took direct command of every P0. Declaration and command are different jobs. Making the declare possible offshore, and then coaching the commanders — including nine I took through in person in India during a structural change — is what kept the rule alive after the season, instead of leaving it as something I remembered.

How I ran it

The order of decisions, written out so the clock is visible.

  1. 01

    I treated the season as the event. A single fallen site was handled as a site. The command problem was the order in which many sites would be restored while the fires were still moving.

  2. 02

    With the Rural Fire Service and the Telco Authority we agreed the list in plain language: critical public sites first, then the rest. Complaint volume did not outrank that list, including when a large customer was loud.

  3. 03

    One bridge held field, the operator and offshore. At every handover I restated the priority so a fresh shift could not quietly replace it with whatever was paging hardest.

  4. 04

    The delay I went looking for was not in the radio. Offshore Tier 1 could see the pattern and still waited for Sydney to declare a major. That gap sits between detection and command, and it costs the sites that are already down.

  5. 05

    The triage was written so they could use it without me. Symptom, site count, public-safety flag. A match meant they declared on the shift. A Sydney morning was no longer part of the path.

  6. 06

    Every P0 still came to me. They owned the decision to declare. I owned the worst of the bridges. The nine incident commanders I coached in India were how that split survived a night shift and a business change, rather than depending on one person in Sydney.

  7. 07

    After the season the rule stayed in the process. A bushfire triage that lives in the incident controller’s head is not a triage. It is a memory, and memories do not roster.